Electricity
SH2 Western Hutt Road 11kV Mains Extension
Client: Northpower (Wellington Electricty)
Location: SH2 Western Hutt Road (Petone)
Description: Installation of 2 x 11kV cables across SH2 immediate to the McKenzie Bridge, including installation of anew 500kV sub station inside 41 Western Hutt Road. The project included extensive site investigation with ground penotrating radar (GPR) and Hydro Excavation before installing the 2 x 125mm OD HDPE pipe by Directional Drill. The 2 x XLPE cables were hauled inside ducting and site reinstated to NZTA standards.
Duration: November - December 2016 (1 month)